- 01
Site survey and programme
Existing conditions are surveyed, and the installation programme, logistics and shutdown windows are agreed with the client and the other trades.
DeliverableMethod statement, installation programme
- 02
Procurement and equipment control
Equipment is ordered against the approved specification and bill of quantities, and submittals, delivery and storage are controlled.
DeliverableMaterial approval list, delivery schedule
- 03
Installation
Cable routes, panels, transformers, generators, busbar trunking and low-current systems are installed to the approved drawings and to IEC 60364-5-52.
DeliverableInstalled works, daily site records
- 04
Integration of low-current and automation systems
Fire detection, CCTV, access control, data and control systems are connected to the power installation and tested at their interfaces.
DeliverableInterface test records
- 05
Verification before energising
Insulation resistance, continuity, earth-fault loop impedance and RCD tests, and functional tests of protection, are carried out to IEC 60364-6.
DeliverableVerification certificate, test records
- 06
Commissioning and handover
Systems are commissioned and staff are trained. As-built drawings, manuals and test records are issued, and maintenance can continue with the same team.
DeliverableAs-built set, O&M manuals, training record